Industrial Projects > Electricity Generation - Gas/Naphtha Based > Dabhol Power Project
Dabhol Power Project
Company: Ratnagiri Gas & Power Pvt. Ltd.
Ownership: Private (Foreign)
Project Location: Village Dabhol,Tal Guhagar, Distt. Ratnagiri, Maharashtra, India
Contact: Neil McGregor / CEO & President
Project Status: Completed Project Type/Scale: New Unit
Industry: Electricity Generation - Gas/Naphtha Based
Investment/Estimated Cost: Rs. 4,477.60 Crores / USD 1,119.40 Million
More projects (By Ratnagiri Gas & Power Pvt. Ltd.):
Ownership: Private (Foreign)
Project Location: Village Dabhol,Tal Guhagar, Distt. Ratnagiri, Maharashtra, India
Contact: Neil McGregor / CEO & President
Project Status: Completed Project Type/Scale: New Unit
Industry: Electricity Generation - Gas/Naphtha Based
Investment/Estimated Cost: Rs. 4,477.60 Crores / USD 1,119.40 Million
| Friday, June 26, 1992 | MoU signed |
|---|---|
| Friday, November 12, 1993 | CEA (Central Electricity Authority) approval received |
| Wednesday, December 8, 1993 | PPA (Power purchase agreement) signed |
| Tuesday, November 22, 1994 | Land acquired |
| Thursday, November 24, 1994 | Date on which environmental clearance was received |
| Sunday, March 31, 1996 | Expenses incurred till 1 (Rs. 836.00 Crores) |
| Tuesday, July 9, 1996 | Cabinet approval received |
| Friday, July 26, 1996 | PPA (Power purchase agreement) signed |
| Tuesday, December 10, 1996 | Financial closure achieved |
| Wednesday, April 30, 1997 | Initial commissioning date |
| Thursday, December 31, 1998 | Revised commissioning date |
| Tuesday, May 25, 1999 | Completed |