Industrial Projects > Railway Transport > Gandhidham-Palanpur Gauge Conversion Project
Gandhidham-Palanpur Gauge Conversion Project
Company: Kutch Railway Co.
Ownership: Private (Indian)
Project Location: Railway Station Building,Churchgate, Mumbai, Maharashtra, India
Contact: O.P. Agarwal / Chief Admn. Officer - Construction
Project Status: Active Project Type/Scale: Renovation - Moderate
Industry: Railway Transport
Investment/Estimated Cost: Rs. 499.70 Crores / USD 124.93 Million
More projects (By Kutch Railway Co.):
Ownership: Private (Indian)
Project Location: Railway Station Building,Churchgate, Mumbai, Maharashtra, India
Contact: O.P. Agarwal / Chief Admn. Officer - Construction
Project Status: Active Project Type/Scale: Renovation - Moderate
Industry: Railway Transport
Investment/Estimated Cost: Rs. 499.70 Crores / USD 124.93 Million
| Sunday, May 31, 1998 | Date of announcement |
|---|---|
| Friday, March 31, 2000 | Expenses incurred till 1 (Rs. 10.00 Crores) |
| Sunday, March 31, 2002 | Expenses incurred till 1 (Rs. 14.36 Crores) |
| Thursday, December 26, 2002 | Foundation stone laid |
| Friday, January 3, 2003 | MoU signed |
| Monday, March 31, 2003 | Expenses incurred till 1 (Rs. 25.57 Crores) |
| Wednesday, March 31, 2004 | Budgetary allocation (Rs. 100.00 Crores) |
| Monday, November 21, 2005 | Financial closure achieved |
| Saturday, December 31, 2005 | Initial commissioning date |
| Friday, March 24, 2006 | Partially commissioned |
| Sunday, December 31, 2006 | Revised commissioning date |
More projects (By Kutch Railway Co.):
| • | Bhuj-Naliya-Sanghipuram Brodgauge Railway Connection |