Kameng Hydel Power Project

Company: North Eastern Electric Power Corpn. Ltd.
Ownership: Central Govt. - Commercial Enterprises
Project Location: Burahgaon, Kameng district, Arunachal Pradesh, India
Contact: P.K. Kakoti / Chairman  Secondary Contact: T C Borgohain / GM

Project Status: Active  Project Type/Scale: New Unit
Industry: Electricity Generation - Hydel Based
Investment/Estimated Cost: Rs. 2,496.90 Crores / USD 624.23 Million
Tuesday, April 30, 1991CEA (Central Electricity Authority) approval received
Thursday, April 1, 1999MoU signed
Thursday, April 6, 2000CEA (Central Electricity Authority) approval received
Monday, June 3, 2002Foundation stone laid
Wednesday, November 24, 2004CCEA (Cabinet Committee on Economic Affairs) approval received
Saturday, December 31, 2005Expenses incurred till 1 (Rs. 269.69 Crores)
Friday, March 31, 2006Expenses incurred till 1 (Rs. 311.54 Crores)
Friday, June 30, 2006Expenses incurred till 1 (Rs. 392.01 Crores)
Tuesday, March 31, 2009Initial commissioning date
Wednesday, August 31, 2011Completion by

More projects (By North Eastern Electric Power Corpn. Ltd.):
• Garo Hills Hydel Power• Kaynsi Hydel Power• Margeritha Hydel Power
• Pare Hydroelectric Power• Garo Hillsthermal Power• Margeritha Thermal Power
• Mawhu Hydro Electric• Pare Hydroelectric Power• West Khasi Hills Thermal Power
• Bhareli Lift Dam - Ii Hydel Power• Doyang Hydel Power• Kameng Dam Power House
• Kopili Hydel I I Power• Kopili Hydel Power• Lower Kopili Hydro Power
• Ranganadi Hydel Power• Ranganadi Hydel Stage Ii Power• Tenga Storage Hydel Power
• Tipaimukh Hydel Power• Tuirial Hydel Power• Lower Kopili Hydro Power
• Tripura-Kopili Transmission Line• Agartala Gas Power• Baramura Power
• Kathalguri Power• Rokhia Power• Tripura (Monarchak) Power
Videos   |   Useful Links   |   FREE Magazines
HomeBuyAdd FREE ListingAdvertise Industrial CompanyIndustrial Portal