Industrial Projects > Pig iron > Pig Iron Project
Pig Iron Project
Company: Kudremukh Iron & Steel Co. Ltd.
Ownership: Central Government
Project Location: India
Project Status: Completed Project Type/Scale: New Unit
Industry: Pig iron
Investment/Estimated Cost: Rs. 328.00 Crores / USD 82.00 Million
More projects (By Kudremukh Iron & Steel Co. Ltd.):
Ownership: Central Government
Project Location: India
Project Status: Completed Project Type/Scale: New Unit
Industry: Pig iron
Investment/Estimated Cost: Rs. 328.00 Crores / USD 82.00 Million
| Monday, May 29, 1995 | Cabinet approval received |
|---|---|
| Saturday, July 1, 1995 | Date of announcement |
| Thursday, February 29, 1996 | Foundation stone laid |
| Thursday, April 30, 1998 | Initial commissioning date |
| Wednesday, June 30, 1999 | Expenses incurred till 1 (Rs. 180.00 Crores) |
| Sunday, February 4, 2001 | Partially commissioned |
| Monday, April 30, 2001 | Revised commissioning date |
| Saturday, November 10, 2001 | Completed |