Industrial Projects > Electricity Generation - Hydel Based > Sewa Hydel I I Project
Sewa Hydel I I Project
Company: Jammu & Kashmir State Electricity Board
Ownership: State Electricity Boards
Project Location: Sewa river,Basholi tehsil, Kathua distict, Jammu & Kashmir, India
Contact: A K Sachdewa / Director - Projects
Project Status: Active Project Type/Scale: New Unit
Industry: Electricity Generation - Hydel Based
Investment/Estimated Cost: Rs. 675.22 Crores / USD 168.81 Million
More projects (By Jammu & Kashmir State Electricity Board):
Ownership: State Electricity Boards
Project Location: Sewa river,Basholi tehsil, Kathua distict, Jammu & Kashmir, India
Contact: A K Sachdewa / Director - Projects
Project Status: Active Project Type/Scale: New Unit
Industry: Electricity Generation - Hydel Based
Investment/Estimated Cost: Rs. 675.22 Crores / USD 168.81 Million
| Friday, December 31, 1999 | Initial commissioning date |
|---|---|
| Monday, December 31, 2001 | Expenses incurred till 1 (Rs. 11.07 Crores) |
| Friday, August 2, 2002 | Project bids awarded |
| Friday, October 18, 2002 | CEA (Central Electricity Authority) approval received (Rs. 675.22 Crores) |
| Friday, March 7, 2003 | Date on which environmental clearance was received |
| Saturday, August 23, 2003 | CCEA (Cabinet Committee on Economic Affairs) approval received |
| Tuesday, September 9, 2003 | Project bids awarded |
| Sunday, October 31, 2004 | Expenses incurred till 1 (Rs. 169.57 Crores) |
| Thursday, March 31, 2005 | Expenses incurred till 1 (Rs. 218.82 Crores) |
| Wednesday, December 31, 2008 | Completion by |
More projects (By Jammu & Kashmir State Electricity Board):
| • | Sawalkot Hydel | • | Uri Hydel Power | • | Baglihar Hydel Power |
| • | Baglihar Stage Ii Hydel Power | • | Kishanganga Hydel Power | • | Sukhnag Hydel Power |
| • | Upper Sindh Hydel Power Project Stage I I |