Company: Mukand Ltd.
Ownership: Bajaj Group
Project Location: Ginigera, Distt. Raichur, Karnataka, India
Contact: R. V. Shah / MD Secondary Contact: R. V. Dalvi / GM - Projects
Project Status: Completed Project Type/Scale: New Unit
Industry: Finished steel
Investment/Estimated Cost: Rs. 400.00 Crores / USD 100.00 Million
More projects (By Mukand Ltd.):
Ownership: Bajaj Group
Project Location: Ginigera, Distt. Raichur, Karnataka, India
Contact: R. V. Shah / MD Secondary Contact: R. V. Dalvi / GM - Projects
Project Status: Completed Project Type/Scale: New Unit
Industry: Finished steel
Investment/Estimated Cost: Rs. 400.00 Crores / USD 100.00 Million
| Tuesday, March 31, 1998 | Initial commissioning date |
|---|---|
| Tuesday, August 18, 1998 | Completed |
| Monday, August 31, 1998 | Commercial production expected |